A supplier wishes to change their bid but can't. How can I allow them to place a new bid?
What's the issue you're facing?
A supplier wishes to change their bid but can't. How can I allow them to place a new bid?
Solution
- Navigate to your event and go to the Participants tab
- Click on the relevant participant to open that supplier
- Open the RFQ tab and find the bid you want to remove
- Click on the red trash bin icon next to the relevant bid, your supplier can now resubmit their bid
Note(s) : You should also be able to do this for sealed events, however if you do not see this optiom please contact Market Dojo support.
Related Articles
How can I allow a participant to change their responses to a questionnaire?
What's the issue you're facing? A participant wishes to edit their response to a questionnaire. How can I allow them to do this? Solution Depending on your companies settings there are a couple of different options here. Option 1 Go to the event and ...
How can I change the event owner?
What is the issue you're facing? I need to change the owner of my event. How can I do this? Solution Only the existing host of the event can transfer ownership to another user. To do this as the current event owner you will need to: 1. Log into ...
What are the minimum and maximum bid change settings for and how do I set these up?
What is the issue you're facing? I need to setup a minumum and maximum bid change. What are these for and how do I set these up? Solution Minimum Bid Change This is the smallest percentage price change that a participant can submit per bid in the ...
How to invite a new participant to your "Live Event"
What is the issue you're facing? I want to invite a new participant to my "Live Event", how do I do this? Solution Please see the below steps on how to invite a new participant to your event after the event has been launched: 1) Firstly you will need ...
How do I create a new Advanced Lot?
What's the issue you're facing? I have selected that I would like to have an Auction or RFQ and now I need to start building my lots using Advanced Lots. How do I do this? Solution On the create Lots tab click on ‘New Lot’ button under the advanced ...